| Province | Subbasin | % |
|---|---|---|
| Blue Mountain | Grande Ronde | 100.00% |
| Previous: | Next: |
|---|---|
| 73982 REL 1: 1998-007-03 EXP GRANDE RONDE SUPPLEMENTATION O&M 2017 |
|
* Expenditures data includes accruals and are based on data through 30-Nov-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Documentation and assistance to support BPA's Environmental Compliance Group. | A: 165. Obtain Permits and submit copies to BPA NEPA group | 12/31/2018 | 12/31/2018 | |
| 2018 Annual Operation Plan | B: 174. Produce 2018 Annual Operating Plan | 03/01/2018 | 02/16/2018 | |
| Acclimate BY 2016 Upper Grande Ronde River spring chinook | C: 176. Acclimate BY 2016 juvenile Upper Grande River River spring chinook | 04/16/2018 | 04/16/2018 | |
| Collect and Spawn BY 2018 Upper Grande Ronde spring chinook | D: 176. Collect and Spawn BY 2018 Upper Grande Ronde River spring chinook | 10/01/2018 | 09/11/2018 | |
| Acclimate BY 2016 Catherine Creek spring chinook | E: 176. Acclimate BY 2016 juvenile Catherine Creek spring chinook | 04/16/2018 | 04/16/2018 | |
| Collect and Spawn BY 2018 Catherine Creek spring chinook | F: 176. Collect and Spawn BY 2018 Catherine Creek spring chinook | 10/01/2018 | 09/11/2018 | |
| Environmental conditions, fish numbers, fish condition, PIT tag information, fish spawned | G: 157. Collection of data at facilities | 12/31/2018 | 12/31/2018 | |
| Data Analysis of Current Data Collection For Management Decisions | H: 162. Data Analysis For Management | 12/31/2018 | 12/31/2018 | |
| Maintain Upper Grande Ronde facilities | I: 61. Upper Grande Ronde Facility Maintenance | 12/31/2018 | 12/31/2018 | |
| Maintain Catherine Creek facilities | J: 61. Catherine Creek Facility Maintenance | 12/31/2018 | 12/31/2018 | |
| Maintain La Grande Shop/Office. | K: 61. La Grande Office/Shop Maintenance | 12/31/2018 | 12/31/2018 | |
| Send weekly reports to co-managers during periods of acclimation and adult facility operation | L: 161. Weekly Facility Activities Reports | 09/30/2018 | 09/17/2018 | |
| Attend meetings for project implementation | M: 191. Coordination of Project Activities | 12/31/2018 | 12/31/2018 | |
| Manage and Administer project | N: 119. Annual Budget Package/Accrual Reports/Provincial Review | 12/31/2018 | 12/31/2018 | |
| Upload 2017 Annual Report | O: 132. Submit 2017 Annual Report - January 2017 - December 2017 | 03/15/2018 | 01/12/2018 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (O. tshawytscha) - Snake River Spring/Summer ESU (Threatened) |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Obtain Permits and submit copies to BPA NEPA group | 01/01/2018 | ||||||
| B | 174 | Produce 2018 Annual Operating Plan | 01/01/2018 | ||||||
| C | 176 | Acclimate BY 2016 juvenile Upper Grande River River spring chinook | 01/01/2018 | ||||||
| D | 176 | Collect and Spawn BY 2018 Upper Grande Ronde River spring chinook | 01/01/2018 | ||||||
| E | 176 | Acclimate BY 2016 juvenile Catherine Creek spring chinook | 01/01/2018 | ||||||
| F | 176 | Collect and Spawn BY 2018 Catherine Creek spring chinook | 01/01/2018 | ||||||
| G | 157 | Collection of data at facilities | 01/01/2018 | ||||||
| H | 162 | Data Analysis For Management | 01/01/2018 | ||||||
| I | 61 | Upper Grande Ronde Facility Maintenance | 01/01/2018 | ||||||
| J | 61 | Catherine Creek Facility Maintenance | 01/01/2018 | ||||||
| K | 61 | La Grande Office/Shop Maintenance | 01/01/2018 | ||||||
| L | 161 | Weekly Facility Activities Reports | 01/01/2018 | ||||||
| M | 191 | Coordination of Project Activities | 01/01/2018 | ||||||
| N | 119 | Annual Budget Package/Accrual Reports/Provincial Review | 01/01/2018 | ||||||
| O | 132 | Submit 2017 Annual Report - January 2017 - December 2017 | 01/01/2018 | ||||||
| P | 202 | BiOp RPA Data for CY 2017 Report | |||||||
| Q | 185 | Quarterly Status Reports | 01/01/2018 |